Email

Related Projects Worldwide

First Turnkey Water Resources Program Financed by USAID National Organization for Potable Water and Sanitary Drainage (NOPWASD) and USAID asked Stanley Consultants to assume the role of design-build contractor and complete the design, subcontract the remaining construction and provide the operation and maintenance services. Learn More
Reviewing the Mississippi River-Gulf Outlet Canal Closure In 2005, Hurricane Katrina sent a surge of water up the Mississippi River-Gulf Outlet (MRGO) Canal flooding many parishes along its banks. As a result, the Inner Harbor Navigational Canal (IHNC) Surge Barrier was built. Learn More
Tunnel Provides USU with Utility Distribution System Stanley Consultants provided comprehensive design services for a new 6,200-foot utility tunnel at the Utah State University. Using a compressed schedule this $22.2 million design-build project was completed in just over 18 months. Learn More
Reducing Greenhouse Gas Emissions In support of the Federal Executive Order 13514, the U.S. Department of Veterans Affairs Hospital in Dallas, TX awarded Stanley Consultants, in design-build partnership with contractor McCarthy Building Companies, the design and construction of a new combined heat and power (CHP) energy center. Learn More
Sewage Improvements among Largest Design-Build Wastewater Projects Stanley Consultants provided engineering services to rehabilitate all trunk sanitary sewers and five wastewater pumping stations for the City of Suez, Egypt. Learn More
Al Dhafra Air Base Force Protection The U.S. Army Corps of Engineers contracted with Stanley Consultants to design an Air Defense Site and Cantonment Area to replace an existing temporary camp and provide adequate protection to USAF personnel. Learn More
Four Bridges Removed and Replaced in 37 Hours for Utah Department of Transportation Stanley Consultants and Wadsworth Brothers Construction teamed up to remove and replace four bridges in an unheard of 37 hours for Utah Department of Transportation. Learn More

Air Force Base Runway Replacement Supports Global War on Terrorism

Stanley Consultants was retained by Perini Corporation as the lead design firm and coordinator throughout design, construction and closeout activities of the Andersen Air Force Base in Guam.

Andersen Air Force Base in Guam serves a key role in supporting both combat and military airlift missions for the Global War on Terrorism. The base's air missions are supported by a pair of two-mile-long runways.  The North Runway project to replace the existing asphalt runway with Portland Cement Concrete (PCC) was completed in 2007.  The 50-year-old South Runway had deteriorated to a point where safe performance of the runway was a significant concern of the military.  Complete removal and replacement of the runway was compulsory.

The $50.6 million runway replacement was awarded as a Design-Build project through the Air Force Civil Engineer Support Agency (AFCESA) to Tutor-Perini Corporation and its local subsidiary, Black Construction Company.  Stanley Consultants was retained by Perini as the lead design firm and coordinator throughout design, construction and closeout activities.

The full project scope included demolition and reconstruction of the existing 11,185 feet by 200 feet South Runway with full (PCC) pavement; repairs and tie-ins to existing taxiway intersections; removal and replacement of degraded airfield lighting; and arresting gear realignment and reconstruction.

Anderson Air Force Base has been the focal point of United States Air Force strength in the Pacific Far East for more than 50 years.  It is home to Pacific Air Forces' 13th Air Force and the 36th Wing, Air Mobility Command's 634th Air Mobility Support Squadron.  The base is one of four Bomber Forward Operating Locations [BFOL] in the Air Force. These locations provide forward support to bomber crews deploying overseas in Europe, Southwest Asia and in the Pacific.