How to Keep a Two-Week Utility Relocation Delay from Becoming a Season-Long Setback

By: Jared Hamilton, P.E., Senior Project Manager, Construction Services Group Manager
November 23, 2026 | 4 min read

Traffic due to ongoing utility relocation on main street

A utility provider's schedule changes. An unexpected conflict requires additional coordination. A relocation takes longer than anticipated. Whatever the cause, the work falls just two weeks behind schedule. It seems like a manageable setback on a major transportation corridor project, but those two weeks can set off a chain of delays that pushes an October completion date into the following spring.

After nearly 30 years on transportation infrastructure projects, I consider utility relocations the biggest source of delays on complex corridor construction projects. I’ve seen the same repeat pattern: a small setback early in construction has significant consequences for the schedule and adds substantial costs for the agency. Managing that risk requires getting involved early, understanding how utility work affects subsequent construction and staying engaged until every relocation is complete.

Start With Field Verification

One of the first things I do when receiving a contract and construction plans is have the utilities located and walk the project corridor.

Plans may show the existing infrastructure, but that doesn’t mean everything in the field will match. We might find two utilities marked on the ground that don’t appear anywhere in the drawings. Before construction advances, we need to determine where those lines go, who owns them and whether they need to be relocated. Discovering an undocumented utility during excavation can create a much bigger problem than identifying it during an initial field review. 

The same attention is necessary after relocation work begins. A utility may have been moved, but is it in the correct location? Is it far enough from the pavement? Does it remain within the right-of-way? Is it deep enough to avoid conflicts with proposed drainage improvements? 

We review those conditions against the agency’s utility permits and the proposed construction plans. Otherwise, we risk learning later that a relocated line still blocks the contractor’s work.

Coordinate the Sequence, Not Just the Schedule

Utility relocation becomes particularly complicated when multiple providers occupy the same corridor.

Consider utility poles carrying attachments for five different companies. Each provider has work to complete before the pole can be removed, and those activities must occur in the proper order. Underground utilities present similar challenges, especially when installation depths and crossings determine which company can work first. I like to bring the utility providers together for weekly coordination meetings to establish that sequence and review upcoming activities. 

But coordinating utility work isn’t simply a matter of asking each provider when it expects to finish. Effective coordination requires understanding how each provider’s work affects the others and what alternatives exist when a schedule slips.

If one provider falls behind, can another move its relocation forward? Can we adjust the sequence to keep crews working rather than waiting on the delayed utility?

Those conversations can prevent a relatively minor setback from affecting the larger construction schedule. I’ve also found that some of the most useful coordination happens outside formal meetings. On a recent project, I made a point of calling individual utility project managers between our weekly meetings. I asked what had happened that week, whether commitments from the previous meeting were being met and what might prevent the next activity from moving forward.

Sometimes the issue was pending a decision from a higher level of the organization. Those one-on-one conversations gave a better understanding of what was happening and where additional coordination was needed. 

Follow Relocations Through Completion

From a construction management standpoint, utility relocation isn’t finished simply because the provider reports its work is complete. We still need to confirm that each installation meets permit requirements, including removal of the old infrastructure, and won’t interfere with the improvements that follow. That means continuing field inspections throughout relocation work and checking completed installations before subsequent construction begins.

Technology is beginning to offer additional ways to evaluate these conditions. Trimble SiteVision, which overlays 3D design models onto field conditions through GPS-enabled mobile devices, allows us to visualize proposed improvements, including underground storm sewers and crossings, while standing in the project corridor. 

As more accurate information about existing underground utilities becomes available, we can use this technology to identify conflicts before they reach construction. For now, we’re still in the early stages of applying it, and field verification remains essential. 

Ultimately, utility coordination is a continuous process that begins before relocation and continues through completion. On a complex corridor project, a missed utility conflict or an improperly sequenced relocation can extend months beyond the original delay. 

The earlier we recognize those issues, the more opportunities we have to keep construction moving. 

Learn more about Stanley Consultants’ construction management services and our experience delivering complex transportation infrastructure projects.